Central Coast Highway Upgrade - Erina Heights, NSW

Project featuring the RECO TerraPlus®; system.

Call Us Now
(02) 9899 2111



General Information

The Carlton to Matcham Road project involved the widening of the Central Coast Highway (HW30) at the Serpentine Road intersection. Located in Erina Heights the aim of the project was to reduce traffic congestion, increase safety to motorists, cyclists, pedestrians and to improve access for public transport.

The project required the design and construction of a 10m high Reinforced Earth™ panel wall to the north of the existing retaining wall (Terramid® segmental Reinforced Earth™ wall), which retains a fill embankment up to 8m high. The project also included substantial ground stabilization, stormwater drainage and subsurface drainage systems, crash barrier and environmental controls.

The system adopted was the RECO TerraPlus® precast concrete facing panel system with a vertical architectural ribbed finish. Key aspects of the design needed to allow for: interaction/global instability with associated existing poor ground conditions and subsequent batter toe slopes; proposed crash barriers and horizontal loadings to be located at the top of the wall; seismic affects; associated drainage pits and services – more specifically the top layers of soil reinforcement needed to be draped down @ 4:1 to avoid these services.

Central Coast Highway Upgrade - Erina Heights, NSW
Central Coast Highway Upgrade - Erina Heights, NSW

Retaining Solutions scope of works involved poor subgrade excavation and replacement and the installation of: concrete footings; architectural ribbed finish panels; REHas soil reinforcement; gravel encapsulated drains and Megaflow drainage system; cement stabilised medium to foundation treatment and underside of crash barrier parapets in addition to surveyor conformance +/- 10mm; spreading and compaction of imported select backfill “Hansen Quarry Dust” which was used within the reinforced fill and general fill zones, partial demolition of existing Terramid® wall to allow for future pavement widening.

The wall construction was completed ahead of schedule due to the close working relationship between Retaining Solutions, RTA Hunter Road Services, Douglas Partners and Hanson quarries.


Like This Project

Project Specs

  • Application - Road Widening
  • Product - RECO TerraPlus® System
  • Finish - Vertical Textured Rib
  • Area - 1190m2
  • Max. Height - 10m
  • Length - 172m
  • Loadings - 20kPa & Crash Barrier
  • Design life - 100 years
  • Owner - NSW RTA
  • Client - Earthtec Construction
  • Construction - 2 months

Featured Case Studies

  • Lisarow Aged Care Facility

    Astoria projects are constructing a new Aged Care Facility at Lisarow, as part of a staged development.... Read more.

  • Central Coast Highway Upgrade

    The Carlton to Matcham Road project involved the widening of the Central Coast Highway (HW30) at the Serpentine... Read more.

  • Cattai Creek
    Glenhaven

    The project involved the construction of 52.1m long & 16.1m wide super-T girder bridge, approach roadworks... Read more.

  • Potts Hill
    Infrastructure Works

    The Potts Hill reservoirs site has been used by Sydney Water for more than 100 years and plays a role in... Read more.